Midcontinent Independent System Operator received federal approval to conduct an expedited review of as many as 68 projects through Aug. 2027 to build new power supply to bolster reliability on the grid stretching from the Upper Midwest area to the Gulf Coast, according to statement Tuesday.
- No more than 10 projects will be studied per quarter
- First window opens Aug. 6-11 and projects will be studied on a first-come, first-served basis; quarterly study to begin Sept. 2
- Federal Energy Regulatory Commission had rejected an earlier version of MISO’s proposed “expedited resource addition study,” or ERAS, in part because it specifically ...