Exxon Delays Golden Pass LNG to Late 2025 on Contractor Dispute

Aug. 2, 2024, 10:30 AM UTC

Exxon Mobil Corp. and QatarEnergy delayed the start of a $10 billion natural gas export project in Texas to the end of next year after lead contractor Zachry Holdings Inc. declared bankruptcy.

The companies agreed other contractors could finish work on Golden Pass last month, paving the way for a restart after several setbacks this year. The new schedule means the 18 million-metric-ton-a-year facility, one of the country’s biggest, will begin operations about six months later than the previous plan, Exxon Chief Financial Officer Kathy Mikells said during an interview.