Dakota Access Builder $4.2b Ohio Pipeline Sparks Concerns

June 22, 2017, 1:07 PM

Energy Transfer Partners LP is making a mess of its biggest project since the Dakota Access pipeline.

Construction of the $4.2 billion Rover natural gas line has caused seven industrial spills, polluted fragile Ohio wetlands and angered local farmers. The company owes $1.5 million in restitution after demolishing an historic house. The Ohio Environmental Protection Agency is furious and a federal energy regulator has launched a rare public investigation that threatens to delay the pipeline’s scheduled Nov. 1 completion.

“We’ve not seen a project in Ohio with spills at this size and scale, and if we can’t even trust Rover ...